Feasibility Survey for Hydroelectric Power Generation and Water Supply
Finca Fila Vista, Tinamastes, Costa Rica
Osa Water Works
Puerto Jimenez, Costa Rica
May 26, 2000
Executive Summary
A detailed field survey of a small portion of the Finca Fila Vista revealed that both electricity and water supply demands can be met from a watershed immediately adjacent to the planned home site. The property in general, and the immediate vicinity of the planned home site in particular, possess the resources to supply more energy and water than a single household could reasonably consume. We were able to prove the viability of the stream on our first day in the field, which gave us the opportunity to collect all the engineering data necessary to design a dual-use system under a large range of desired daily energy and water output. In this report we have presented a conceptual design of a system that may be adequate to the future home's electric demand. We have sized a system with a charging potential of 60 kW/day with a continuous available output of 15 kW and will present a bid for its installation upon authorization. However, before doing all the detailed design work necessary to prepare the bid, we need to know if the design output is satisfactory to the home owner. If it is not, we can design the system according to the projected demands. The window of opportunity to guarantee implementation of the proposed design will end in the last week of August. Osa Water Works will be able to perform the complete installation of the dual-use design during a two-week period, ideally in the month of July.
Introduction
Water and energy represent two of the most basic demands by home builders and owners. These fundamental needs are particularly relevant in remote building sites, where neither basic commodity can be taken for granted. In areas that receive a large amount of rainfall and have significant topographical relief, it is possible to implement dual-use water supply / hydroelectric generation systems that provide comprehensive answers to the questions of water and energy demands. The Tinamastes region of Pacific Costa Rica is an area that has an abundance of potential hydroelectric generation sources. At the Finca Fila Vista, there are several streams that could reasonably supply all the electrical demands of a single dwelling. Given the breadth of the property, it might additionally be possible to combine the hydroelectric potential from dispersed sources to supply the power demands of entire communities. This feasibility evaluation was undertaken on the basis, however, of the energy and water demands of a single home.
Objective
The objective of this study was three-fold:
Methods
Investigative methods included the assimilation of verbal reports, the physical inspection of promising watersheds, and the detailed surveying and characterization of a target stream.
Our field methods of investigation consisted of collecting data by a variety of means. Simple surveying methods employing a tape measure, inclinometer, compass, and trigonometric formulae were used to determine distances, slopes, and to calculate vertical drops. Corroboration was obtained with an instrument that measures positive and negative pressure over a known linear distance. Flow measurement was accomplished by measuring the time taken to fill a known volume. Water quality samples collected from the spring were preserved and transported to San Jose for analysis by Laboratorios Aqylasa. Interpretation of the water quality results will be provided in a following report.
Location
The study area included the immediate vicinity of the planned building site shown below.
Figure 1. Location of study area. (adapted from the Dominical Quadrangle)
.
The topographic map of the area has a scale too small to work from and is shown in Figure 1 simply as a reference. A copy of the plano encompassing the study area is shown at the top of the following page for additional detail.
Figure 2. Plano of the property containing proposed hydroelectric/water supply system.
Hydrological Overview
|
The Tinamastes region of Costa Rica is blessed by an enormity of hydroelectric potential as a result of two unrelated factors: 1) the abundance of water, and 2) active tectonic uplift. Water is the universal solvent in a chemical sense but also has an enormous physical erosive power as well. In the presence of abundant water, such as in the Tinamastes region and many other parts of Costa Rica, there is a high rate of chemical and physical weathering of the land surface. This rate of natural weathering is increased by the high biologic activity of the local ecosystem and the highly efficient nature of the tropical food chain. Tectonic uplift, however, is equally important in shaping the geomorphology and consequent hydrology of the region. Due to the subduction of the Cocos Plate off the Costa Rican west coast, Pacific Costa Rica is rising at globally significant rates. These existing mountain-building forces provide the power for the carving of steep mountainsides, gullies, and canyons by aggressive rivers. The clearest physiographic example in the study area is the Fila Tinamastes (shown to the right), which is a regionally significant fault escarpment. The combination of abundant water and regional tectonic uplift provides for high-flow, high-energy streams, which represent ideal potential sources for hydroelectric power generation and dead-ringers for water supply. |
|
Onsite Hydrological Survey Results
Interviews with personnel with lifelong familiarity with the property encompassed by the Finca Fila Vista revealed the availability of three potential hydroelectric/water supply sources near the anticipated home site. Two of these water sources were hiked, and the stream shown in Figure 2 was identified as a primary target stream. This stream was the closest to the anticipated home site and by all verbal reports had the greatest discharge of all subjacent streams during both seasons and in drought.
The target stream has a confluence of two major tributaries in a location about 1000 feet from the planned home site. Since these two tributaries are major sources of the stream's flow, the ideal location for a hydroelectric pipeline water intake is below the confluence of the tributaries. Fortuitously, the stretch of river immediately beneath the confluence of these tributaries is ideally suited for the installation of an infiltration gallery for the intake of water necessary to charge the hydroelectric pipeline (Figure 4). A resident of the area of over 30 years reports that the target stream has never dried up. He reports that in the worst drought in memory the target stream shrank to only about one third of the size it presented during the survey. Approximately 100 linear feet and 25 vertical feet beneath the proposed hydroelectric water intake lies a freshwater spring emerging from bedding planes and fractures in solid rock adjacent to a small waterfall. This spring appears to be an excellent source of domestic, irrigation, and pool water supply (Figure 5). About 930 linear feet and 205 vertical feet lower lies the location where we would place the hydroelectric generator for a system with a charging potential of 60 kW per day.
Figure 4. Proposed location of the infiltration gallery for the intake of the hydroelectric pipeline.
Figure 5. Spring emerging from rock face (proposed water supply).
Whereas the conceptual design presented herein depends upon a vertical drop of only 270 feet, it is practical on the basis of our findings to extend the scope of the project by siting the power generation installation farther downstream. The versatility presented by the land surface characteristics of the property in question makes it possible to refine the system design if the energy and water supply of the conceptual design are deemed insufficient by the property owner.
One of the fundamental design variables of generating hydroelectric energy is the flow rate of the stream that provides the force to drive the hydroelectric turbine. Ideally, this flow measurement should be taken in the driest time of the year. Although rains had begun in the area the week before the survey, the stream water was free of turbidity, indicating that ideal base flow conditions were in effect at the time of flow measurement. Flow rates of the target stream and the spring intended for potable water supply were measured by confining the existing flow through pipes, making all efforts to minimize the losses around the piping employed. Pipe discharges were then measured by filling a known volume during a measured period of time. Results of the discharge measurement are presented in Table 1.
Table 1. Measured flow rates of the target stream and the proposed water supply.
|
HYDROELECTRIC SUPPLY |
300 GPM |
|
POTABLE WATER SUPPLY |
3.5 GPM |
Figure 6. Flow measurement of target stream.
|
|
The final critical design parameter for a hydroelectric generation system is the amount of available vertical drop, which determines the water pressure that drives the turbine. To determine the vertical drop available and the resulting length of the penstock, or pipeline, needed for installation of this system, the target stream was surveyed from the site of the proposed infiltration gallery downstream. The results of this survey are shown in Figure 7.
Figure 7. Land surface profile from the proposed hydroelectric pipeline intake location to the proposed generation point.
Discussion
The amount of power available to any hydroelectric system depends on the following variables: 1) dynamic head (in feet), which is equal to the vertical drop from the source to the power-generation site; 2) the rate of water flow (gpm); 3) pipeline efficiency (cumulative head losses); and 4) the efficiency of the turbine/generator, or "Pelton wheel," which is typically 50% for DC turbines. We used a design flow rate of 120 gpm, which is about 1/3 of the target stream's measured flow, which corresponds to the lowest flow observed during drought conditions. We sized the system to provide 270 feet of head. Using an estimated friction coefficient of 0.18, this corresponds to a charging source equivalent to 60 kW per day.
Power in Watts = (head)*(flow rate)(friction coefficient)*(Pelton wheel efficiency)
Power in Watts = (270)*(120)*(0.18)*(0.50) = 2916 watts continuous / 69.9 kW per day
We propose a system which utilizes a single pipeline feeding twin turbines. The force of water is directed at the runners (Pelton wheels) through a diffusion system which focuses 4 individual nozzles on the runner of each machine. In this fashion, we are able to maximize electrical output (90 kW/day) during times of high flow rates by operating the full array of nozzles, or increase the efficiency of a single machine to operate at near maximum output (40 kW/day) in times of unseasonably low flow. This system will consist of a DC generating source which will, in turn, charge a bank of batteries sized adequately to meet an emergency demand of at least one week of autonomy, in the unlikely event a system error were to occur. The Trace inverting system will draw from the battery bank, providing 110/220 volt three-phase power to meet the demands of the household.
In contrast, a typical AC generation system of comparable output requires flow rates of water large enough to meet the maximum surges placed on the system. Oftentimes this requires flows of thousands of gallons per minute and sensitive and costly monitoring systems, which are not often designed to hold up well in these types of environments. The DC charging system, on the other hand, is easily serviceable, efficient, and cost effective.
We expect to increase the observed spring water supply discharge from its present flow rate of 3.5 gpm to at least twice that much and possibly more. We have included a 5000 gallon water storage tank in our design that will ensure an adequate water supply even during periods of high water usage, such as when filling the swimming pool.
Proposed Conceptual Design
A block diagram of the components of the proposed hydroelectric design is given in Figure 8. Physical structures that must be built for the hydroelectric system design include: 1) a small dam at the intake location for installation of the infiltration gallery in the stream channel; 2) a concrete housing for the two parallel Pelton generators at the end of the pipeline; 3) power station (site of DC-AC inversion and battery storage unit); and 4) a small utility structure at the planned home site for housing the AC system's main breaker and water pressure tanks. Figure 9 illustrates the proposed water system, which includes the following physical structures/equipment: 1) a spring collection box built in the rock face where the spring is located, 2) a water storage tank equipped with a submersible pump, and 3) main AC breaker box enclosure and pressure tank storage at the planned home site.
Figure 8. Block diagram showing the basic components of the hydroelectric generation system under proposal.
Figure 9. Block diagram showing the basic components of the proposed water supply system.
Conclusions and Recommendations
Power and water demands for a large, single-residence dwelling can be supplied through hydroelectric power generation and spring water supply. We have presented a conceptual design that will result in a charging source of 60 kW/day and the potential for a continuous supply of 15 kW. We will provide a detailed design and bid for the complete installation of the system upon the authorization to proceed. If greater power demand is anticipated, we will design and bid a system according to the demands that are anticipated. Osa Water Works has a window of opportunity for installation of a finalized design during a two-week period in the month of July. Sistema Solar Internacional, S.A., a member of OWW, has a container of equipment coming from the United States in end of June, which makes it possible to have all the components in place for a July installation date. Due to existing work loads, travel schedules, and the heavy rains that begin in September, if the work cannot proceed in July or August, then we may not be able to install a system until December or January. We will complete the installation in a 15-day time period. The final installation can be left indefinitely in an idle state and be ready to turn on when construction efforts begin. We recommend that the home owner provide us with an authorization to proceed with bidding the 15 kW continual system introduced herein or to provide us with an alternate desired output. We will be able to turn around a detailed bid for installation of the system within 1week of authorization.
Home Mission Hydroelectric Power Potable Water Sanitation Contact Us Ask OWW