Hydroelectric Power Generation
Engineering, Design, and Economic Analysis
For: [-------------],
Carate, Costa Rica
By: Osa Water Works, S.A.
October 9, 2002
Introduction
This document
includes a feasibility analysis for the installation of an AC-Direct
hydroelectric system for providing continuous electrical power to [-redacted-]. A
system design and quote for procurement and installation follows.
Data Summary
Previous field
investigations by [-redacted-] identified the most viable approximate pipeline
trajectory for the development of hydroelectric power generation from the one
stream with sufficient year round flow to provide for continuous hydroelectric
power generation. The land surface profile of the trajectory is shown below.

At the time of the
survey a stream flow of 120 gpm was approximated at the optimal site for
deployment of the hydroelectric water intake. As shown in the graph above, the
vertical relief from the intake point to the optimal generation point is 640
feet. At the 68% efficiency of the AC turbine contemplated for this
installation, half the observed flow can be diverted for hydroelectric
generation of 4.7 kW. Although the survey was undertaken during the rainy
season, conditions during and preceding the survey were unseasonably dry. A
water flow measurement made in the dry season (March 16, 2002) by [-redacted-]
personnel revealed a flow rate of 62 gpm, which means that in the driest time of
the year all of the flow would have to be diverted to achieve comparable power
generation. Verbal reports from [-redacted-] personnel suggest that the flow
observed on the day of the survey (10/5/02) is either sustained or exceeded in
all but one or two months (March and April) of the dry season. Average flows
are considerably larger during most of the year and capable of sustaining much
greater power generation rates.
On the basis of the
information collected and that provided by [-redacted-] personnel, an AC-direct
mini-hydro system can be sustained year round on the basis of the measured flows
and vertical relief. A system design has been prepared that will enable the
generation of power based on a range in flow from 40 gpm to 120 gpm, which
corresponds to a theoretical hydroelectric power generation potential ranging
from 3.1 kW/hour to 9.4 kW/hour. It is expected that the average annual
production will be in the range of 7 kW/hour on the basis of seasonal rainfall
distribution and the actual power demands of the facility.
A conceptual design
of the system under proposal is presented below.

System components
are described briefly below:
-
Intake.
Water is to be captured by a proprietary water intake infiltration gallery
developed by Osa Water Works. The infiltration gallery and coffer dam
provide for the collection of water in the stream sediments of the river
being developed. The infiltration gallery is guaranteed maintenance free
and has a usable life expectancy, barring acts of God, measured in decades.
-
Pipeline.
A three-inch diameter PVC pipeline is proposed in order to accommodate the
flow required and to minimize the pipe friction losses expected over the
approximate 4000 foot length of the pipeline. Because the anticipated
static pressure varies from 0 to 278 psi, OWW recommends the installation of
PVC pipe of three different pressure ratings: 160 psi, 250 psi, and 350 psi
(see diagram above).
-
Hydroelectric Plant.
An AC-Direct 3-10 Kw/hour mini-hydro power generator with adjustable nozzle
diameter will provide for power generation throughout the flow regime from
60 gpm up to 200 gpm. It is anticipated that during most of the year this
nozzle will be set to provide for 7 kW/hour, thus exceeding the actual
facility power demand under normal power usage conditions. During dry
months, when power generation potential is lower, it will be necessary to
reduce the nozzle size accordingly. Attentive facility management of power
consumption patterns may also be required. During high flow conditions, the
nozzle can be opened if desired to boost power output up to a ceiling of
around 10 kW/hour.
-
Power Bodega.
A simple one-story concrete structure measuring 8 feet by 12 feet will house
the hydroelectric generator.
-
Transmission Cable.
The final component of the system is a run of 1,182 feet of electrical cable
from the hydroelectric bodega to the lodge. Whereas this cable can be
either buried in conduit or run above surface, the quote that we have
prepared is for the least expensive alternative, above surface power
transmission.
Scope of Work.
The project will consist of the following job elements:
-
Materials and Equipment
Procurement.
-
Fabrication of infiltration
gallery in Puerto Jimenez.
-
Construction of power bodega
-
Installation of infiltration
gallery and coffer dam
-
Installation of pipeline
-
Installation of power
transmission cables.
-
Delivery and installation of
hydroelectric power generator
-
Commissioning, testing, and
training.
Budget
The table below
details the materials required and a budget for turnkey system installation.

Time Line
The table below provides a time line for completion of key project elements.
Due to the relative danger of the work required for pipeline installation, OWW
is not prepared to deploy its pipeline crew for this job during October and
November owing to the potentially life-threatening interference of heavy rains
with the highly difficult nature of pipeline installation along semi-vertical
forest mountainsides. Since the generator must be custom manufactured, there is
an unknown lag time in delivery. Preliminary pipeline, intake, and bodega
construction could be undertaken as early as December.
Economic Analysis
The cost of the
proposed power system was used as the basis for an economic analysis of the
proposed hydroelectric power generation system. Economic comparisons of the
hydroelectric alternative were made for two cases: 1) Diesel power generation
that produces power output comparable to that of hydroelectric power
generation; and 2) Actual patterns of diesel power generation at
[-redacted-].
Parameters common to both that were used for the analysis included the
following:
-
Useful life of hydroelectric
system: 20 years
-
Diesel Generator Value:
$12,000
-
Mean Diesel Value:
$2.00/gallon
-
during useful life: 2 times
-
Fuel Consumption for
generator: 1 gallon per hour
-
Dollar Inflation: 0 % per
year
-
Amortization: Assume
depreciation is constant across useful life of system.
-
Backup Generator Replacement
during useful life: 1 time.
-
Diesel Generator Operation
to supplement hydro: 5 % of operation without hydro.
-
Hydroelectric Generator
Replacement: $6000
-
Value of money: For the
sake of expediency and transparency of the analysis, the interest rates of a
loan to offset capital outlay and the interest accrued by investing
comparable capital in secure investments as an alternative were not factored
into the economic analysis that follows.
The parameters specific to the
two regimes of generator usage that are compared with the hydroelectric
alternative are listed in the table below.
|
Economic Analysis Parameter |
Comparable Power |
Actual Usage Patterns
|
|
Diesel generator
replacement |
2 |
1 |
|
Time Generator Turned On
/ Day |
24 |
10 |
|
Annual generator
maintenance |
1000 |
500 |
Calculations
-
Comparable Power:
Total cost of
full-time diesel power generation for 20 years.
-
Generator replacement:
$24,000
-
Generator maintenance:
$20,000
-
Fuel Consumption:
$350,400
-
Total Cost: $394,000
-
Annual Cost: $19,720
-
Actual Usage Patterns:
Total cost of diesel power generation assuming current usage patterns.
-
Generator replacement:
$12,000
-
Generator maintenance:
$10,000
-
Fuel Consumption:
$146,000
-
Total Cost: $168,000
-
Annual Cost: $8,400
-
Hydroelectric Alternative:
Total cost of hydroelectric alternative over useful life.
-
Hydroelectric capital
cost: $45,640
-
Hydroelectric
maintenance: $6,000
-
Total Cost: $51,640
-
Annual Cost: $2,582
-
Investment Pay Off
-
Comparable: 2.6 years
-
Actual: 6.1 years
-
Annual savings After Pay Off
-
Comparable: $17,138
-
Actual: $5,818
-
Cost / Benefit Analysis.
The costs of
hydroelectric and diesel power generation are outlined above. However, the
benefits include additional considerations that cannot easily be assigned
monetary value. These are detailed below.
-
Renewable Resource
Utilization.
Mini-hydro systems have been declared in the most recent global
environmental summit in Johannesburg as a renewable resource. Diesel,
of course, is a fossil fuel and is a non-renewable resource.
Implementation of mini-hydroelectric power generation at [-redacted-] is,
therefore, an exercise in responsible planetary stewardship. In a more
mercantilistic vein, since [-redacted-] is an “Eco-Lodge,” hydroelectric
power generation represents a de facto marketing tool.
-
Emissions.
Diesel fuel, beyond being a non-renewable energy resource, emits upon
combustion carbon dioxide, carbon monoxide, and a variety of nitrogenous
compounds, all of which are greenhouse gases. Hydroelectric power
generation has no emissions whatsoever, and has no effect on climate
change. In addition to exercising responsible planetary stewardship, a
reduced greenhouse gas emissions operation is a strong marketing tool
for an Eco-Lodge.
-
Maintenance.
Maintenance requirements of hydroelectric power generation equipment is
nominal.
-
Noise.
Although the hydro turbine does make noise, it is considerably less
noise than what is emitted by a power generator, and the location of the
proposed power bodega is so isolated as to never impose upon lodge
guests.
-
Transport.
Beyond the cost of diesel, its transport to the lodge is a very real
expense (which was not factored into the economic analysis presented
above). The savings in time and effort of filling drums at the gas
station, transport, and unloading at [-redacted-] are appreciable,
particularly over the useful life of the system. The hydroelectric
power generation system is self-supporting and requires no transport
once the system is installed.
-
Value Added.
A functional hydroelectric power generation system increases the value
of both [-redacted-] and the property upon which it is located.
Conclusions
On the basis of the
economic analysis presented, it is apparent that the hydroelectric alternative
is clearly favorable from both a mid- and long-term perspective. Even in the
short term of five years or less, the hydroelectric alternative carries such
ancillary benefits (both aesthetic and practical) as to warrant serious
consideration. When the increase in the value of the facilities and property is
factored into consideration, it is almost certain that the hydroelectric
alternative is the economically favorable alternative.